All overhead utilities in this congested downtown alley were converted to underground and the site was restored with stamped asphalt, decorative railings, and plantings. All secondary conductors were routed through custom manholes to facilitate future service upgrades. All three-phase electrical services were converted to 120/208V and all services were converted to underground.
Engineering services included:
- Inventory of all electrical equipment including customer owned for voltage conversions
- Underground system design
- Lighting design
- Material procurement
- Communication utility coordination
- Construction staking
- Construction inspection
- Customer outage coordination
- Assistance with site restoration