City of Petoskey

Project consisted of the underground conversion of 3.0 miles of primary & secondary electrical distribution system plus voltage conversion to 12.5kV.

This project replaced an aged overhead 4.16kV distribution system with a new looped underground 12.5kV distribution system including all electrical services within the project boundaries. The project incorporated multiple critical loads including a wastewater treatment plant, regional hospital and large medical facility.

Engineering services included:

  • Project planning & cost estimating
  • ROW Procurement
  • Underground system design
  • Material procurement
  • Bidding & contract documents
  • MDOT Permitting
  • Construction observation
  • Switching & outage coordination
  • Record drawings
  • Closeout documentation

Additional Info

  • Project: 12.5kV Distribution Underground & Voltage Conversion (Charlevoix Avenue)
  • Client: City of Petoskey
  • Location: Petoskey, Michigan
More in this category: City of Petoskey »