Marquette Board of Light & Power

Project consisted of the underground conversion of one-half mile of primary & secondary electrical distribution system.

This project replaced a double circuit overhead 12.5kV distribution system with a new looped underground 12.5kV distribution system including switchgear, sectionalizing cabinets, transformers, & building services. The project was completed as part of a municipal urban revitalization project along the Lake Superior shoreline.

Engineering services included:

  • Project cost estimating
  • Underground system design
  • Material procurement
  • Bidding & contract documents
  • Construction observation
  • Record drawings
  • Closeout documentation

Additional Info

  • Project: South Rail Yard 12.5kV Distribution Conversion to Underground
  • Client: Marquette Board of Light & Power
  • Location: Marquette, Michigan
More in this category: « Lowell Light & Power